Author: Subject: MS Project Problem-Can anyone Help
liam.mccaffrey

posted on 5/10/11 at 01:55 PM Reply With Quote
MS Project Problem-Can anyone Help

I'm having trouble with a project file. trying to set up a project based on tasks that take multiples of half days 1, 2, 3.5, 7.5 etc and on a working week of M,T,W,T,F and a half day saturday where weekdays are obviously 1 day duration.

However i seem to set things up I can get things right. It keeps pushing the end of each task into the morning of the next day. So by the by the end of a 4 month program I'm over by weeks and weeks. If I set up a 1 day task it finishes on the following morning bumping the end of its dependent task into the middle of the third day.

Another example is I have a 7.5 day task which is showing on the gantt chart as a 10 day task despite being entered as a 7.5 day task on the duration pane on the left.

I'd previously set this up graphically in excel using shaded cells which worked great, but I'm losing the will to live on project!!!!

Can anyone help?!!?!?!?

[Edited on 5/10/11 by liam.mccaffrey]

[Edited on 5/10/11 by liam.mccaffrey]





Build Blog
Build Photo Album

View User's Profile View All Posts By User U2U Member
HowardB

posted on 5/10/11 at 02:14 PM Reply With Quote
MS Project bases it calcs on a 5 - 2 week, and so 7.5 days would show as a week and a half,.....

u2u if you want to email me a file to play with,...





Howard

Fisher Fury was 2000 Zetec - now a 1600 (it Lives again and goes zoom)

View User's Profile View All Posts By User U2U Member
scudderfish

posted on 5/10/11 at 02:30 PM Reply With Quote
And there was me thinking this'd be about Megasquirt

Project is the spawn of the devil and a great example of the difference between precision and accuracy ("This project will end at 11:23am 05/06/2013 because MSP says so!", very precise, very unlikely to be accurate.)






View User's Profile View All Posts By User U2U Member
HowardB

posted on 5/10/11 at 02:36 PM Reply With Quote
quote:
Originally posted by scudderfish
And there was me thinking this'd be about Megasquirt

Project is the spawn of the devil and a great example of the difference between precision and accuracy ("This project will end at 11:23am 05/06/2013 because MSP says so!", very precise, very unlikely to be accurate.)




Me too, but I have to use Micros$t evil son of satan, so might be able to confuse the situation a little further





Howard

Fisher Fury was 2000 Zetec - now a 1600 (it Lives again and goes zoom)

View User's Profile View All Posts By User U2U Member
MikeR

posted on 5/10/11 at 02:51 PM Reply With Quote
open the calendar and set up your default working week to include 4 hours on saturday.

Enter your tasks as hours.

Schedule on hours not days.

(if that doesn't work - get someone who knows what they're doing involved).

View User's Profile View All Posts By User U2U Member
liam.mccaffrey

posted on 5/10/11 at 04:26 PM Reply With Quote
I think I have it sorted now, albeit by fudging. Thanks for your help chaps

[Edited on 5/10/11 by liam.mccaffrey]





Build Blog
Build Photo Album

View User's Profile View All Posts By User U2U Member

New Topic New Poll New Reply


go to top






Website design and SEO by Studio Montage

All content © 2001-16 LocostBuilders. Reproduction prohibited
Opinions expressed in public posts are those of the author and do not necessarily represent
the views of other users or any member of the LocostBuilders team.
Running XMB 1.8 Partagium [© 2002 XMB Group] on Apache under CentOS Linux
Founded, built and operated by ChrisW.