Simon
|
posted on 8/4/14 at 06:16 PM |
|
|
Building work costs
Ok, I need a trench for foundations digging, filling with concrete and then three walls building. One wall (2.6m long) with be brick and block, the
other two (3m long) will be single skin. All around 2.7 metres high and incl wall plate. Nothing else to do as I'll do the roof
I've had some quotes including materials - what do you reckon they are?
Certainly amused me - to the extent I'll probably do it myself (but not the brickwork) !
ATB
Simon
|
|
|
tegwin
|
posted on 8/4/14 at 06:17 PM |
|
|
Now that is going to depend where you are....
But I should say the cost would be around £8k?
------------------------------------------------------------------------------------------------------------------------
Would the last person who leaves the country please switch off the lights and close the door!
www.verticalhorizonsmedia.tv
|
|
jossey
|
posted on 8/4/14 at 06:36 PM |
|
|
Leeds 5k
Thanks
David Johnson
Building my tiger avon slowly but surely.
|
|
SteveWalker
|
posted on 8/4/14 at 06:46 PM |
|
|
If you've got the time, it's amazing how quickly you can begin to do a decent (if slow) job of bricklaying. From never doing any
bricklaying other than refixing the top row of a garden wall, I started laying bricks and blocks using a "Bricky" tool, after a while I
progressed to doing it without and finally had done 900 bricks and 120-something blocks. It took me a fair few weekends, but it was mid-winter and I
had two pillars, plus a pillar with a 50° angle in the middle and two angled end to it, which slowed things down somewhat.
|
|
hootsno1
|
posted on 8/4/14 at 07:30 PM |
|
|
A good brickie should do that in about 3/4 days as for the footings I did mine over a weekend with my wife and kids doing the wheel barrows and 2, 7
yard skips
My footings were 1.9mts deep and 600 wide the first 2 foot was good digging and good soil and used that to level my garden then had the concrete
deliverd on the Monday all in cost me £2300 that was 6 years ago
Hope this helps
Cheers
Mark
If a little hammer won't fix it get a bigger hammer
|
|
Barkalarr
|
posted on 9/4/14 at 07:50 AM |
|
|
Using the £1000 per sq metre which seems the be the universal building price guide, I'd say 7k complete.
Minus a couple of k for the roof, I'd say between £4000 and £5000
|
|
Simon
|
posted on 9/4/14 at 07:58 PM |
|
|
One of the quotes
To supply all materials and Labour for the above works:
* PRICE: £7.700
We will require an initial deposit of £4,000 to place orders for materials, and this will secure an agreed start date, then payments will then need to
be paid as follows:
1. At the end of the first week a payment of £1,000
2. On the last day the remainder will need to be paid
Er, a deposit for a credit account at builder's merchants. Yeah, feck off!
The other:
Footings:
Dig out footings as per plans
Muckaway
Infill with concrete
Place polythene membrane
Place insulation and concrete
Placing of required drainage
Clear all rubbish and leave in clean and tidy state
Price: £2,915 Inclusive of labour and materials
Extension:
Build extension to plate height in brick/blockwork as per plans
Placing of wall ties
Cavity fill with insulation
Clear all rubbish and leave in clean and tidy state
Price: £1,100 Labour only
Bit more like it, but there's still a £1500 worth of materials to go on that!
Maybe I'm just tight
ATB
Simon
|
|